MOA Partnership of Peoples Renewal Project fonds
Print preview Hierarchy View:

MOA Partnership of Peoples Renewal Project fonds

  • 150
  • Fonds
  • 1998 - 2010

MOA’s Partnership for the Peoples Renewal project (MRP) was a multi-year major expansion and renovation project, undertaken to enhance physical, visual and virtual access to MOA collections in order to better facilitate ongoing research. The project lasted from 2004-2010, and cost approximately $55.5 million. It was funded in large part by a Canada Foundation for Innovation (CFI) grant. Additional funds came from provincial (British Columbia) grants, a Museums Assistance Program (MAP), and the University of British Columbia. Prior to the launch of the MRP, MOA’s thirty year old infrastructure was no longer able to successfully serve the increasing demands of its communities and users due to insufficient space to safely store or display material, to acquire new acquisitions, or to conduct research

Renovations included a new research wing, new offices, laboratories, a culturally sensitive research room, recording studio, and a new exhibition hall (The Audain Gallery). Other enhancements included MOA's new Multiversity Galleries, the creation of the Reciprocal Research Network (RRN), expansion of the Museum Shop, a new cafe, and courtyard and outdoor events area.

The work of the MRP was carried out by different streams: Program Wide stream, Building stream, Collections Research and Enhancement Project (CREP), the Reciprocal Research Network (RRN), and the Laboratory of Archaeology stream. Records in the fonds are divided into series based on these streams.

The MRP had physical and virtual components. The physical components included:
• Expanding the building (from approx.. 50,000 square feet to 120,000 square feet)
• Creation of spaces suitable for interdisciplinary and collaborative community-based research
• New 5,600 square foot exhibition space
• A redesign and expansion of visible storage into the “Multiversity Galleries”
• Expanded capacity for direct object study through the creation of research suites
• New large object storage rooms for textiles, works on paper, and three dimensional works
• New offices for staff
• New chemistry lab
• New library and archives space
• Installation of a Museum cafe
• Expansion and relocation of the Museum Shop

Virtual components included:
• Development of the Reciprocal Research Network (RRN)
• The digitization of MOA’s object collection, and development of an online catalogue to make these images and object information accessible.
• Consultations with originating communities regarding the handling and description of MOA’s object collection

Major roles in the MRP included:
• Jill Baird (MOA staff) – Project Lead,
• UBC Properties Trust (especially Joe Redmond and Rob Brown) – The University’s development arm given responsibility to build all UBC buildings. Involved in review and approval of design and budget, including UBC Board approvals
• Lundholm Associate Architects (Michael Lundholm, Lead) – Museum architect and planning specialist. Worked on initial plans with MOA in early phase, and did the feasibility study.
• Stantec Architecture Limited (Noel Best, lead) – The architectural firm that designed the building and interior spaces renovations and additions, in consultation with Arthur Erickson (architect of the original building)
• David Cunningham – Lead project designer
• Ambit Consulting (Dan Zollmann) – Provided program management consultation for non-building components of MRP
• Goppion - Italian company that made the new cases that went in the Multiversity Galleries

Program Wide

Includes records produced by or related to the Program Wide stream of the Renewal Project (MRP). The purpose of this stream was to “provide overall program management for the MRP and its streams, and to capture the objectives and scope elements which, being common to all or most of the streams, would be more effectively managed in a consolidated manner.” The objectives of the Program Wide stream were:

• To ensure that the MRP aligns with and delivers on the strategic objectives of the Museum as outlined in the MRP objectives to the fullest extent possible
• To work with First Nations communities, other program collaborators, and MOA’s diverse communities to deliver the MRP in a manner that is in accordance with the guiding principles and vision of the Museum.
• To optimize the allocation of bother human and financial resources to maximize the overall effectiveness of the program.
• To implement information technology systems that integrate with each other, are sustainable, and support the mission of the Museum and the objectives of the renewal program.
• To ensure the Museum remains operational and functional throughout as much of the renewal program as possible.
• To ensure relevant funding agencies are satisfied with both the process and the outcomes of the MRP.
(Purpose and objectives of the Program Wide stream are from the MRP Program Scope Definition, 1.2.)

Jill Baird was the Program-Wide stream lead.

Material in the series includes early planning documents, budgets, committee and other meeting minutes, correspondence, records related to various sources of funding and staffing, communication with UBC and the University’s Board of Directors, records related to First Nations community consultations and partnerships, PR and communications documents, and records related to IT planning.

The series is divided into subseries based on the various functions of the Program Wide stream.

Results 1 to 20 of 313